Language Studies International purchased the space as a commercial coop and awarded B&B Contracting Group, working along with the design team at Lori Kupfer Architect and the engineering team of Lilker Associates, to build out the space within 12 weeks. An entire new HVAC system was installed from scratch with exterior window louvers, two new AC units, all exposed sheet metal and a fully automated self-contained BMS system allowing full real time climate control with remote internet access to the system. The space is largely divided with sound deadening glass wall partitions and acoustically insulated drywall partitions. Because the space was technically changed from “office” use to “classroom” use, the space required a new Certificate of Occupancy. Documentation and tracking systems were instrumental in providing the expeditors what they required in a timely manner.